DATE: December 2, 2026
TO: Honorable Mayor and City Councilmembers
FROM: Water Utilities Department
TITLE: APPROVE Change Order 6 To The Public Works Agreement With Burtech Pipeline, Inc., to perform full width alley pavement replacement FOR the downtown water and sewer replacement, phase 2 project AND APPROPRIATE FUNDS FOR SAME
RECOMMENDATION
title
Staff recommends that City Council approve Change Order 6 to the Public Works agreement with Burtech Pipeline, Inc., in the amount of $2,926,000, for a revised contract amount of $30,812,204, to perform full width alley pavement replacement within the Downtown Water and Sewer Replacement - Phase II Project limit; appropriate $1,726,000 from the Water- and Sewer- Fixed Asset Replacement funds unrestricted reserves; and authorize the City Engineer to execute the Change Order upon receipt of all supporting documents.
body
BACKGROUND AND ANALYSIS
The Downtown Water and Sewer Replacement - Phase II (Project) is the second of five planned phases for water and sewer replacement in the downtown area. Phase II includes 3 miles of sewer main replacement and over 2.5 miles of water main replacement. The Project also expands the recycled water system with nearly a mile of new recycled water main in the downtown area.
On December 17, 2025, Council approved contract award to Burtech Pipeline, Inc. (Contractor), in the amount of $27,061,128 for the construction of the Downtown Water and Sewer Replacement - Phase II Project; and authorized the City Engineer to execute change orders up to 15 percent of the construction contract in the amount of $4,059,169. Notice to Proceed was issued on March 2, 2026, and to date the Contractor has installed over 18,000 feet combined of new water, sewer, and recycled water.
Approved Contract Change Orders 1-5 total $825,076 using Council approved contingency funds. Work completed under these change orders includes additional protective measures for water services and fire hydrants, various design changes due to unforeseen conditions, additional water main replacement required based on condition assessment and field conflicts, and field retrofits to meet County of San Diego Department of Environmental Health and Quality requirements.
Over 12,300 feet of scheduled pipeline replacement is within city alleys, many of which exhibit significant existing pavement deterioration and surface drainage issues. Additionally, the City has received multiple complaints from residents in the area concerned with the pavement condition and lack of drainage. The anticipated El Niño emergency heightens concerns, as these alleys will further deteriorate throughout the impacts of a heavy storm season.
The contract documents currently only require paving of the pipeline trench line and will not remedy the current pavement and drainage concerns in the alleys. The Water Utilities Department proposes to replace the full width of these alleys, to provide a long-term condition and drainage solution. The Public Works department partnered with Water Utilities and have agreed to contribute funding for a portion of this paving work.
FISCAL IMPACT
The additional paving work is outside the scope of the original contract, and to preserve the original project contingency, staff recommend that council approve a change order in the amount of $2,926,000 without using existing contingency funds. Public Works will contribute for the alley paving repairs portion in the amount of $1,200,000 which will be charged to the Capital Improvement Program (CIP) account shown in the table below. Staff is requesting to use Water and Sewer reserves in the amount of $1,726,00. With the approval of change order 6, the total authorized construction Contract amount will be $30,812,204, and the total remaining contingency amount will be $3,234,094.
|
Description |
Amount |
Requested Appropriation |
Account Number |
Funding Source |
Available |
|
Change Order 6 Water Fund |
|
$863,000 |
DwnTwn Wtr Pipeline Ph 2 of 5 908135716712.5703.10600 |
Water FAR Unrestricted Reserves 712.3100.0002 |
$76.3M |
|
Change Order 6 Sewer Fund |
|
863,000 |
DwnTwn Swr Pipeline Ph 2 of 5 909136716722.5703.10600 |
Sewer FAR Unrestricted Reserves 722.3100.0002 |
$143.5M |
|
Change Order 6 Public Wks Fund |
$1,200,000 |
|
Misc. Street/ Slurry Seal 425426212.5703 |
|
$2.3M |
|
Change Order 6 Total |
$1,200,000 |
$1,726,000 |
|
|
|
Water Fixed Asset Replacement Fund 712, Sewer Fixed Asset Replacement Fund 722, and TransNet Fund 212 are the funding sources for this project. Sufficient funding balances are available in the funds to support their respective portions of this change order.
COMMISSION OR COMMITTEE REPORT
The Utilities Commission approved staff’s recommendation at its regularly scheduled meeting on November 17, 2026.
CITY ATTORNEY’S ANALYSIS
Purchases must comply with Chapter 28A of the City Code.
end
Prepared by: Neil Irani, Senior Civil Engineer
Reviewed by: Fredrick Mayo, Water Utilities Director
Submitted by: Jonathan Borrego, City Manager
ATTACHMENTS:
1. Change Order 6
2. Alley Repair Location Map
3. City of Oceanside Pavement Condition Index Map