DATE: December 2, 2026
TO: Honorable Mayor and City Councilmembers
FROM: Development Services Department
TITLE: CHANGE ORDER WITH A.B. HASHMI FOR THE MANCE BUCHANON DOG PARK - PHASE 1 PROJECT
RECOMMENDATION
title
Staff recommends that the City Council approve a construction change order with A.B. Hashmi, Inc. (“Contractor”), in the amount of $126,041, for a total contract amount not to exceed $275,941, for additional construction services for the Mance Buchanon Dog Park - Phase 1 and authorize the City Engineer to execute the change order.
body
BACKGROUND AND ANALYSIS
In 2018, the City’s only public off-leash dog park was closed, prompting the community to request a replacement facility. As part of the FY 2021-22 Capital Improvement Program, several potential dog park locations were evaluated, and Ron Ortega Park was initially selected for design. The City entered into a professional services agreement for design work; however, as staff continued evaluating the site, it became clear that additional information, coordination needs with multiple regulatory agencies, and long-term uncertainties at the location would significantly affect project delivery. The Ron Ortega site was subject to the requirements of the San Diego County Environmental Health Department due to the proximity of a closed landfill site, which rendered this location particularly challenging.
Due to the challenges encountered at the Ron Ortega site, staff began exploring alternate dog park locations. Through a dog park feasibility study completed in 2021, Mance Buchanon Park was ranked highly among the public outreach conducted. As a result, staff reassessed Mance Buchanon Park as an option. The Mance Buchanon dog park site presents fewer constraints than Ron Ortega and can be delivered sooner and with available funding. It’s important to note that a fenced dog park was included in the original conceptual plan for Mance Buchanon Park but was not constructed during initial development.
As previously shared with Council, staff has embarked on a planning process for the Mance Buchanon site. Based on the estimated construction cost, the project qualified for the informal bid process under the City’s Procurement Policy (AD-21). Bid documents were distributed to qualified contractors, and multiple bids were received by the deadline. A.B. Hashmi, Inc. submitted the lowest responsive and responsible bid, in the amount of $149,900. On September 15, 2026, the Public Works Agreement was executed by the City Engineer under the Uniform Public Construction Cost Accounting Act (UPCCAA) authority.
Following award, staff identified several design refinements necessary for long-term functionality of the dog park, including the incorporation of dog-friendly water fountains and additional fencing. These improvements were originally anticipated as part of a future second phase of the project; however, because initial bids came in lower than anticipated, staff determined that incorporating the elements now would avoid future disruption. As these enhancements were not included in the original bid scope, a contract change order is required to complete the work.
FISCAL IMPACT
The Change Order No. 1 with the Contractor in the amount of $126,041 will be charged to the Dog Facilities Study Account, which has a current available balance of $196,041. Therefore, sufficient funds are available.
|
Description |
Account |
Construction Change Order Cost |
Available Balance |
|
Change Order No. 1 |
Dog Facilities Study 906165220598.5703.10800 |
$126,041 |
$196,041 |
COMMISSION OR COMMITTEE REPORT
Does not apply
CITY ATTORNEY’S ANALYSIS
The referenced documents have been reviewed by the City Attorney and approved as to form.
end
Prepared by: Edwin Medina, Associate Engineer
Reviewed by: Lillian Doherty, Development Services Director
Submitted by: Jonathan Borrego, City Manager
ATTACHMENTS:
1. Construction Change Order No. 1