Title:
|
Staff recommends that the City Council approve Amendment 3 to the Professional Services Agreement (PSA) with The Lightfoot Planning Group, in the amount of $19,958, for a revised contract amount not to exceed $282,845, for construction support and a design change related to the proposed El Corazon Phase II Trails Project; and authorize the City Manager to execute the amendment upon receipt of all supporting documentation.
|
DATE: September 17, 2025
TO: Honorable Mayor and City Councilmembers
FROM: Development Services Department
TITLE: AMENDMENT 3 TO THE PROFESSIONAL SERVICES AGREEMENT FOR THE EL CORAZON PHASE II TRAILS PROJECT
RECOMMENDATION
title
Staff recommends that the City Council approve Amendment 3 to the Professional Services Agreement (PSA) with The Lightfoot Planning Group, in the amount of $19,958, for a revised contract amount not to exceed $282,845, for construction support and a design change related to the proposed El Corazon Phase II Trails Project; and authorize the City Manager to execute the amendment upon receipt of all supporting documentation.
body
BACKGROUND AND ANALYSIS
In 1994, approximately 465 acres of a former sand mine property were donated to the City. In 2003, the City began a planning process that culminated in the adoption of the El Corazon Specific Plan ("Specific Plan"), which divided the site into six districts, including a Habitat District featuring a multi-phase trail system.
Phase I of the Habitat District Trails was completed in 2016 and includes one mile of public nature trails along Garrison Creek.
On January 6, 2021, the City awarded a PSA to The Lightfoot Planning Group for design and environmental review of the proposed Phase II portion of the trail system. This included obtaining all environmental and discretionary approvals and preparing construction drawings. The proposed Phase II trail system would develop approximately 1.72 miles of multi-use trails, and include:
* A 12-foot-wide paved surface for pedestrians, cyclists, and other non-motorized uses; and,
* A 4-foot-wide unpaved surface intended primarily for runners.
On December 15, 2022, and July 4, 2024, the City administratively executed Amendments No. 1 and No. 2, respectively, to the PSA to extend its expiration date.
Following the completion of the proposed Phase II design, staff solicited construction bids; however, after further analysis of the site's geological conditions, the trail alignment was subsequently modified in coordination with public input due to geotechnical considerations.
Amendment 3 would enable The Lightfoot Planning Group to provide the City with construction support and execute a design change to implement the revised Phase II Trail alignment.
Upon City Council approval of the proposed amendment, staff anticipates beginning construction during the current non-nesting season for birds (September 15 through February 15).
ENVIRONMENTAL REVIEW
Not applicable.
FISCAL IMPACT
The current scope of the contract was completed with approximately $44,002 remaining in the contract. The remaining scope of work is estimated to cost $63,960. Therefore, staff is requesting an increase in the not to exceed contract of $19,958 through Amendment 3.
Amendment 3 to the PSA, in the amount of $19,958, includes additional services to support construction and a design change to implement the revised trail alignment. The cost of Amendment 3 will be charged to the El Corazon Trails Phase II account 912168420501.5703.10100, which currently has an available balance of $557,358 Therefore, sufficient funding is available.
Description
Amount
El Corazon Trails Phase 2
912168420501.5703.10100
Amendment 3
$ 19,958
$ 19,958
Available Budget
$ 557,358
COMMISSION OR COMMITTEE REPORT
Does not apply.
CITY ATTORNEY'S ANALYSIS
The referenced documents have been reviewed by the City Attorney and approved as to form.
end
Prepared by: Kymberly Corbin, Senior Civil Engineer
Reviewed by: Darlene Nicandro, Development Services Director
Submitted by: Jonathan Borrego, City Manager
ATTACHMENTS:
1. Staff Report
2. Amendment 3 to PSA