Title: Staff recommends that the City Council approve Amendment 6 to the Professional Services Agreement (PSA) with Schmidt Design Group, in the amount of $26,800 for a revised contract amount of $770,000, to perform additional design services for the Supul Park (Formerly El Coraz?n Park Site 1) project; and authorize the City Manager to execute the amendment upon receipt of all supporting documents.
Attachments: 1. Amendment 6 to PSA
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE:  August 5, 2026

 

TO:                       Honorable Mayor and City Councilmembers

 

FROM: Development Services Department

TITLE:
AMENDMENT 6 TO THE PROFESSIONAL SERVICES AGREEMENT WITH SCHMIDT DESIGN GROUP FOR THE DESIGN OF SUPUL PARK (FORMERLY El CORAZON PARK SITE 1)

 

RECOMMENDATION

title

Staff recommends that the City Council approve Amendment 6 to the Professional Services Agreement (PSA) with Schmidt Design Group, in the amount of $26,800 for a revised contract amount of $770,000, to perform additional design services for the Supul Park (Formerly El Corazón Park Site 1) project; and authorize the City Manager to execute the amendment upon receipt of all supporting documents.

body

BACKGROUND AND ANALYSIS

 

On February 23, 2022, the City Council approved a PSA with Schmidt Design Group, in the amount of $476,360, for the design of the proposed Supul Park Project.

 

On January 25, 2023, the City Council approved Amendment 1 to the PSA, in the amount of $25,750, to provide additional public outreach and bilingual translation services.

 

On June 26, 2024, the City Council approved Amendment 2 to the PSA, in the amount of $81,730, to include preparation of a mass grading plan, complete the design of wet and dry utilities, and provide survey services.

 

On September 11, 2024, the City Council approved Amendment 3 to the PSA, in the amount of $38,650, to prepare construction documents for sports field lighting on the multi-purpose fields and hard courts, as well as security cameras near the restroom facilities.

 

On April 23, 2025, the City Council approved Amendment 4 to the PSA, in the amount of $113,000, to provide for necessary work for design revisions and optional services such as signage design and value engineering services. At the same meeting, the City Council also approved a purchase order with American Ramp Company in the amount of $1,000,000 for the design-build of the pump track.

 

On November 19, 2025, the City Council approved Amendment 5 to the PSA, in the amount of $7,710, to prepare construction documents for lighting at the pump track.

 

Amendment 6 allocates the existing funding for as-needed services to support recycled water permit processing so the site will be ready when recycled water becomes available at a future, but currently unknown, date.  Amendment 6 also provides additional funding to address site drainage and stormwater requirements identified during the City’s review process. This work included additional coordination and review of nearby projects and drainage information to support the proposed design approach and reduce the need for significant modifications to the current park design.

 

Staff anticipates bringing a Public Works Agreement to the City Council for construction of Supul Park in Fall 2026.

 

FISCAL IMPACT

 

Amendment 6 to the PSA is in the amount of $26,800. The total cost will be charged to El Corazon Park Site 1 account 906177722598.5305.10400. This account has an available balance of $1,639,593; therefore, sufficient funds are available.

 

Description

Amount

Account

Available Balance

Amendment 5

$26,800

El Corazón Park Site 1 Design 906177722598.5305.10400

$1,639,593

 

 

COMMISSION OR COMMITTEE REPORT

 

Does not apply.

 

CITY ATTORNEY’S ANALYSIS

 

The referenced documents have been reviewed by the City Attorney and approved as form.

end

 

 

Prepared by: Kymberly Corbin, Senior Civil Engineer

Reviewed by: Brian Thomas, Acting Development Services Director                                                                                    

Submitted by: Jonathan Borrego, City Manager                                                                                                                               

 