Title: Staff recommends that the City Council approve Amendment 2 to the public works agreement with Brax Company, in the amount of $55,725, for a total contract amount not to exceed $655,725, for additional material and labor necessary to complete the rehabilitation of a production well at Mission Basin Groundwater Purification Facility; and authorize the City Manager, or designee, to execute the amendment.
Attachments: 1. Staff Report, 2. Amendment 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE:  May 6, 2026

 

TO:                       Honorable Mayor and City Councilmembers

 

FROM: Water Utilities Department

TITLE: 
AMENDMENT TO PUBLIC WORKS AGREEMENT WITH BRAX COMPANY FOR REHABILITATION OF PRODUCTION WELL AT MISSION BASIN GROUNDWATER PURIFICATION FACILITY

 

RECOMMENDATION

title

Staff recommends that the City Council approve Amendment 2 to the public works agreement with Brax Company, in the amount of $55,725, for a total contract amount not to exceed $655,725, for additional material and labor necessary to complete the rehabilitation of a production well at Mission Basin Groundwater Purification Facility; and authorize the City Manager, or designee, to execute the amendment.

body

BACKGROUND AND ANALYSIS

 

The Mission Basin Groundwater Purification Facility treats groundwater water to produce about 10% of the City’s drinking water.  Part of the treatment process includes eight production wells that supply the groundwater to the plant. These wells must be rehabilitated approximately every two to three years to maintain production flow.

Production Well 2 is in the process of being rehabilitated which involves pump maintenance and screen cleaning.  During this process, Brax, the company performing the well rehabilitation, notified staff that more production flow would be possible if the pump could be lowered toward the bottom of the well (using three sections of pipe). Lowering the pump further down into the well by approximately 60 feet would allow the well pump to operate with greater efficiency.

Brax has provided a quote in the amount of $55,725 for this work.  The quote  includes material, equipment rental, taxes, estimated freight, and additional bonds.

FISCAL IMPACT

 

Amendment 2 in the amount of $55,725 will be charged to the Mission Basin Groundwater Purification Facility account 750755711.5320 which has a current balance of $182,026; therefore, sufficient funds are available.

Account Number

Amount

Available Balance

750755711.5320

$55,725

$182,026

 

Water Meter Fees and Service charges in the Water Operating Fund (711) are the source of funds for this purchase.

 

COMMISSION OR COMMITTEE REPORT

 

The Utilities Commission approved staff’s recommendation at a special  meeting held on April 15, 2026.

 

CITY ATTORNEY’S ANALYSIS

 

Purchases must comply with Chapter 28A of the City Code. The referenced documents have been reviewed by the City Attorney and approved as to form.

end

 

Prepared by: Rudy Guzman, Water Utilities Manager

Reviewed by: Frederick Mayo, Water Utilities Director                                                                                                         

Submitted by: Jonathan Borrego, City Manager                                                                                                                               

 