Legislation Details

File #: 26-1786    Version: 1
Type: Agreement Status: Consent Agenda
File created: 11/3/2026 In control: City Council
On agenda: 12/2/2026 Final action:
Title: Staff recommends that the City Council approve a Public Works Agreement (PWA) and purchase order, in the amount of $347,165 to Potential Electrical Design Services, Inc., for the Construction of Electrical Vehicle (EV) Charging Stations at the City’s Operations Center (COC); appropriate funds in the amount of $69,433 from the General Fund Infrastructure account for the City’s portion; authorize the Financial Services Director to execute the purchase order; and authorize the City Manager, or designee, to execute the agreement upon receipt of all supporting documents.
Attachments: 1. Staff Report, 2. Potential Electrical Design Service, Inc. PWA, 3. SDGE Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE:  December 2, 2026

 

TO:                       Honorable Mayor and City Councilmembers

 

FROM: Public Works Department

TITLE: 
PUBLIC WORKS AGREEMENT AND PURCHASE ORDER FOR THE CONSTRUCTION OF ELECTRIC VEHICLE CHARGING STATIONS AT THE CITY OPERATIONS CENTER

 

RECOMMENDATION

title

Staff recommends that the City Council approve a Public Works Agreement (PWA) and purchase order, in the amount of $347,165 to Potential Electrical Design Services, Inc., for the Construction of Electrical Vehicle (EV) Charging Stations at the City’s Operations Center (COC); appropriate funds in the amount of $69,433 from the General Fund Infrastructure account for the City’s portion; authorize the Financial Services Director to execute the purchase order; and authorize the City Manager, or designee, to execute the agreement upon receipt of all supporting documents.

body

BACKGROUND AND ANALYSIS

 

The COC, located at 4927 Oceanside Boulevard, will require an electric vehicle charging station to accommodate the growing demand generated by the City’s expanding electric vehicle fleet. As the home of Fleet Division operations, the facility functions as a central hub where multiple City departments will be able to charge City vehicles and access essential maintenance services.

 

On June 3, 2026, the City Council approved the purchases of EV charging stations, hardware and software for $263,564. Of this amount, $201,650 is anticipated to be funded through a voucher awarded to the City under the Department of Energy’s Energy Efficiency and Conservation Block Grant (EECBG) program, subject to project completion and verification of compliance with program requirements. 

 

On September 21, 2026, the City posted a formal bid for Electric Vehicle Charging Station installation at the City Operations Center. Five bid submittals were received with Potential Electrical Design Services, Inc. being the lowest bidder. Below is a table of all bids received.

Re-Gen Electric, Inc.

$693,935

Motive Energy

$447,710

J+B Contracting, Inc.

$396,300

Potential Electrical Design Services, Inc.

$347,165

Zetroc Electric, LLC

$508,483

 

The City of Oceanside is participating in the San Diego Gas and Electric’s (SDG&E) Power Your Drive for Fleets Make Ready Infrastructure Program which provides a rebate of up to 80% of the cost to design and to install the EV charging infrastructure. The City is responsible for the remaining 20% of the cost of installing the charging stations.

 

 

FISCAL IMPACT

 

The purchase order with Potential Electrical Design Services, Inc., in the amount of $347,165, will be charged to the accounts as shown in the table below.  The SDG&E rebate of 80% will be deposited into EV Chargers Construction-SDG&E Rebate account 807206826270.4381 after the SDG&E has verified the installation of the chargers. Staff is requesting that a budget of $277,732 be appropriated to revenue 807206826270.4381 and  expense 807206826270.5305 to the SDGE rebate account. Additionally, an appropriation in the amount of $69,433 for the City Match will be required from the General Fund Infrastructure account 101.3020.0054.

 

Description

Amount

Appropriate

Account

Funding Source

Available Balance

Potential Electrical Design Services, Inc.

$277,732

$277,732

807206826270.4381 807206826270.5305  EV Charges Construction - SDGE Rebate

 

$277,732

 

$69,433

$69,433

907206826501.5305.10600 EV Chargers Construction - City Match

General Fund Infrastructure 101.3020.0054

$26.4M

Total

$347,165

 

 

 

 

 

 

A transfer of $69,433 is required from account 1101.6900.0501 to 907206826501.6800.0101.

 

 

COMMISSION OR COMMITTEE REPORT

 

Does not apply.

 

 

CITY ATTORNEY’S ANALYSIS

 

The bid documents and PWA were reviewed by City Attorney and approved as to form. The contract must be awarded to the lowest responsive and responsible bidder. The Public Contract Code defines “responsible bidder” as a bidder who has demonstrated the attributes of trustworthiness as well as quality, fitness, capacity and experience to satisfactorily perform a public works contract. The City Council also has the discretion to reject all bids and re-advertise.

end

 

Prepared by: Casey Van Der Linden, Fleet Manager

Reviewed by: Hamid Bahadori, Public Works Director                                                                                                         

Submitted by: Jonathan Borrego, City Manager                                                                                                                               

 

ATTACHMENTS:

1.                     Potential Electrical Design Services, Inc. PWA

2.                     SDGE Agreement