File #: 25-786    Version: 1
Type: Agreement Status: Passed
File created: 4/24/2025 In control: City Council
On agenda: 5/21/2025 Final action: 5/21/2025
Title: Staff recommends that the City Council approve a Public Works Agreement (PWA) with Johnson Controls, in an amount of $64,790, for the replacement of three existing Network Automation Engines (NAE); authorize the City Manager to execute the agreement upon receipt of all supporting documents; and authorize the Financial Services Director, or designee, execute the purchase order.
Attachments: 1. Staff Report, 2. Johnson Controls Proposal, 3. All Proposals

DATE:  May 21, 2025

 

TO:                       Honorable Mayor and City Councilmembers

 

FROM: Public Works Department

TITLE:  PUBLIC WORKS AGREEMENT AND PURCHASE ORDER FOR THE REPLACEMENT OF HVAC AUTOMATION NAE CONTROLLERS AT THE CIVIC CENTER BUILDING COMPLEX

 

RECOMMENDATION

title

Staff recommends that the City Council approve a Public Works Agreement (PWA) with Johnson Controls, in an amount of $64,790, for the replacement of three existing Network Automation Engines (NAE); authorize the City Manager to execute the agreement upon receipt of all supporting documents; and authorize the Financial Services Director, or designee, execute the purchase order.

body

BACKGROUND AND ANALYSIS

 

The Civic Center Building chiller and all Heating, Ventilation and Air Conditioning (HVAC) temperature controls throughout the complex are controlled by an existing proprietary Johnson Control (JCI) Metasys system consisting of four NAE controllers. The existing building automation system will be upgraded from the current JCI Metasys system to a new Tridium automated system. One of the NAE controllers, which solely runs the chiller operation, is due to be replaced through the ENGIE chiller replacement project. The other three NAE controllers, which currently control temperatures throughout the complex, will become obsolete with the migration of the new Tridium operating system. Therefore, these three NAE controllers will need to be replaced in order for the full HVAC controls to work flawlessly after the migration to the new open-source Tridium based system is complete.

 

The Public Works Department currently has two existing purchase orders with Johnson Controls for boiler/chiller maintenance and extras for repairs in the combined amount of $58,263. The requested PWA, in the amount of $64,790, for the replacement of the NAE controllers, brings the cumulative total with Johnson Controls, Inc. over $100,000, requiring Council approval.

 

Staff obtained quotes for the purchasing and installation of the three new NAE Controllers at the Civic Center Building complex in accordance with the City’s Procurement of Goods and Services Directive. Three contractors responded with quotes for the new NAE upgrades and installations and Johnsons Controls, Inc.’s submitted lowest quote in the amount of $64,790.

 

 

FISCAL IMPACT

 

The PWA with Johnson Controls, in the amount of $64,790, will be charged to the City Building Maintenance account 630603851.5704. The City Building Maintenance account has an available balance of $424,899; therefore, sufficient funds are available.

Description

Amount

Account Number

Available Balance

 Johnson Controls PWA

 $64,790

City Building Maintenance Account 630603851.5704

  $424,899

 

COMMISSION OR COMMITTEE REPORT

 

Does not apply.

 

CITY ATTORNEY’S ANALYSIS

 

Purchases must be made according to the procedures set forth in Chapter 28A of the City Code. The referenced documents have been reviewed by the City Attorney and approved as to form.

end

 

Prepared by: Tony Visco, Senior Building Maintenance Supervisor

Reviewed by: Hamid Bahadori, Public Works Director                                                                                                         

Submitted by: Jonathan Borrego, City Manager                                                                                                                               

 