DATE: June 3, 2026
TO: Honorable Mayor and City Councilmembers
FROM: Public Works Department
TITLE: RESOLUTION CONFIRMING THE ASSESSMENTS FOR FISCAL YEAR 2026-27 AND ORDERING THE ASSESSMENTS TO BE LEVIED FOR FISCAL YEAR 2026-27 FOR THE OCEANSIDE LIGHTING DISTRICT, ASSESSMENT DISTRICT NO. 2-1991
RECOMMENDATION
title
Staff recommends that the City Council adopt a resolution approving the Engineer’s Report confirming the diagram and assessments and ordering the assessments to be levied for FY 2026-27 for the Oceanside Lighting District, Assessment District No. 2-1991.
body
BACKGROUND AND ANALYSIS

The Oceanside Lighting District ("District") was formed in 1991 pursuant to the authority granted by the Landscaping and Lighting Act of 1972 of the California Streets and Highways Code. The formation of the District eliminated the eight separate lighting districts covering various sections of the City of Oceanside ("City") and provides the means to finance the operation and maintenance of the street lighting system on the City’s public streets.
Each year the City Council is required to conduct a public hearing regarding the proposed fiscal year assessments to be levied within the District. The public hearing provides all interested persons an opportunity to be heard, either in writing or orally at the public hearing, regarding the renewal and assessments. Since the formation of the District the assessments for the property owners within the District have remained the same.
On May 6, 2026, the City Council adopted Resolution 26-R0242-1 approving the Engineer's Report for the annual renewal of the District. The Engineer’s Report has not been modified and is attached hereto. As part of the public hearing process regarding the proposed FY 2026-27 assessments to be levied within the District, after consideration of the evidence submitted, the City Council is requested to adopt resolutions confirming the diagram and assessments for FY 2026-27. The assessments are based on a formula containing costs associated with both general and local benefit zones as shown in Exhibit B of the Engineer's Report. The public hearing provides all interested persons an opportunity to be heard, either in writing or orally at the public hearing, regarding the renewal and assessments.
The general benefit zone is comprised of the streetlights located on the prime, major and secondary arterials. The general benefit zone costs, which include the City's share of the state freeway and highway lighting costs for these streets, are assessed against each parcel of land within the District. The local benefit zone is comprised of property which fronts or adjoins a collector or local street. Property within this zone is assessed its proportionate share of the costs associated with the lighting system as well as its share of the general benefit zone costs. The benefit units assigned to a parcel are based on similar factors used to calculate the City's thoroughfare fees. The use of the property is the determining factor in the corresponding benefit unit assignment. Single-family residential homes are assigned 10 benefit units whereas shopping centers are assigned 500 benefit units per acre.
An itemized outline of District costs, including the calculation of the average annual assessment per benefit unit, is summarized in the Engineer's Report. Exhibit C of the Engineer's Report includes the proposed assessments to be levied against each lot and parcel of real property within the District. Exhibit C is available for review in the City Clerk's office. The City Council is required to conduct a public hearing regarding the proposed FY 2026-27 assessments to be levied within the District.
At this time, the current amount of revenue generated from the levy of the annual assessments is sufficient to cover the cost to effectively operate and maintain the street lighting system within the District. The assessments levied within the District have not been increased since 1991, the year the District was formed. A single-family residence is assessed $15.80 annually. Although the assessment rates have not increased since 1991, the District expenditures have increased over the years. Electric consumption is one of the largest components of the overall expenditures that have steadily increased. Currently, the cost to provide electricity to operate the approximately 8,452 streetlights within the District is approximately $79,562 per month. Also, as new development occurs, additional streetlights that are installed add to the operational expenses.
The annual assessments are entered on the property tax roll, collected by the County of San Diego and deposited into the District Fund. The total amount of the anticipated revenue is $1,650,480 and expenditures are anticipated to be $1,181,659 for FY 2026-27 pursuant to the Engineer’s Report.
A Citywide streetlight retrofit project to convert all streetlights from high-pressure sodium to LED was completed in December of 2014. The retrofit project had a lease in place since that time in the amount of $476,209. The lease was paid off in December 2025, thereby eliminating this expense within the Lighting District.
FISCAL IMPACT
The revenue in the amount of $1,650,480 and the expense appropriations in the amount of $1,181,659 are included in the proposed FY 2026-27 budget shown within Exhibit B of the Engineer’s Report.
COMMISSION OR COMMITTEE REPORT
Does not apply.
CITY ATTORNEY’S ANALYSIS
The referenced documents have been reviewed by the City Attorney and approved as to form.
end
Prepared by: Vicki Gutierrez, Real Estate Manager
Reviewed by: Hamid Bahadori, Public Works Director
Submitted by: Jonathan Borrego, City Manager
ATACHMENTS:
1. Resolution with Approved Engineer’s Report, including Exhibits