DATE: December 2, 2026
TO: Honorable Mayor and City Councilmembers
FROM: Water Utilities Department
TITLE: APPROVE CHANGE ORDER 6 TO THE PUBLIC WORKS AGREEMENT WITH BURTECH PIPELINE, INC., TO PERFORM FULL WIDTH ALLEY PAVEMENT REPLACEMENT FOR THE DOWNTOWN WATER AND SEWER REPLACEMENT, PHASE 2 PROJECT AND APPROPRIATE FUNDS FOR SAME
RECOMMENDATION
title
Staff recommends that City Council approve Change Order 6 to the Public Works agreement with Burtech Pipeline, Inc., in the amount of $2,926,000, for a revised contract amount of $30,812,204, to perform full width alley pavement replacement within the Downtown Water and Sewer Replacement – Phase II Project limit; appropriate $1,726,000 from the Water- and Sewer- Fixed Asset Replacement funds unrestricted reserves; and authorize the City Engineer to execute the Change Order upon receipt of all supporting documents.
body
BACKGROUND AND ANALYSIS
The Downtown Water and Sewer Replacement – Phase II (Project) is the second of five planned phases for water and sewer replacement in the downtown area. Phase II includes 3 miles of sewer main replacement and over 2.5 miles of water main replacement. The Project also expands the recycled water system with nearly a mile of new recycled water main in the downtown area.
On December 17, 2025, Council approved contract award to Burtech Pipeline, Inc. (Contractor), in the amount of $27,061,128 for the construction of the Downtown Water and Sewer Replacement – Phase II Project; and authorized the City Engineer to execute change orders up to 15 percent of the construction contract in the amount of $4,059,169. Notice to Proceed was issued on March 2, 2026, and to date the Contractor has installed over 18,000 feet combined of new water, sewer, and recycled water.
Approved Contract Change Orders 1-5 total $825,076 using Council approved contingency funds. Work completed under these change orders includes additional protective measures for water services and fire hydrants, va...
Click here for full text