Title: Staff recommends that the City Council determine there remains a need to continue emergency work on the 18-inch Mesa Loma Water Main.
Attachments: 1. Staff Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DATE: September 17, 2025

TO: Honorable Mayor and City Councilmembers

FROM: Water Utilities Department

TITLE: APPROVE CONTINUATION OF EMERGENCY WORK TO REPAIR THE 18-INCH MESA LOMA WATER MAIN AT LOMA ALTA CREEK

RECOMMENDATION
title
Staff recommends that the City Council determine there remains a need to continue emergency work on the 18-inch Mesa Loma Water Main.
body
BACKGROUND AND ANALYSIS

In January 2024, staff isolated a leaking segment of the 18-inch Mesa Loma Water Main near Loma Alta Creek and activated the Mesa Loma Pump Station to maintain service.
Emergency permits were secured in early 2025 from the U.S. Army Corps of Engineers, San Diego Regional Water Quality Control Board, and NCTD. Cass Arrieta, the City's emergency contractor, began work in April 2025. Initial repairs addressed significant damage to the pipeline within the creek, and subsequent inspections revealed additional deficiencies in multiple joints near the initial repair site.
To address these, staff revised the repair strategy to install a trenchless, high-pressure liner. Advantage Reline, Inc. commenced liner work in late August 2025. Cass Arrieta is providing trench support, flushing, testing, and final tie-ins. All work is anticipated to be completed by the end of September 2025 under the City's emergency procurement policy.
FISCAL IMPACT
Funding is from the Water Fixed Asset Replacement Fund (712), charged to the Water Pipeline Replacement Account 908163620712.
The current total estimated project cost is $1,528,872, covering construction, rehabilitation, engineering, permitting, and support services.
Staff will return with a final report at project completion including a full accounting of actual costs and will recommend replenishing the Cass Arrieta emergency account by $100,000 to maintain readiness for future emergencies.


ENVIRONMENTAL IMPACT

The Project is located in an environmentally sensitive area. All required permits and notifications have been secured, and sta...