File #: 25-676    Version: 1
Type: Purchase Order Status: Passed
File created: 3/11/2025 In control: City Council
On agenda: 5/7/2025 Final action: 5/7/2025
Title: Staff recommends that the City Council approve a purchase order to Romtec, Inc. ("Romtec"), in an amount not to exceed $554,973, for final design and supply of building material for the structures at the proposed El Corazon Park Site 1 and authorize the Financial Services Director, or designee, to execute the purchase order.
Attachments: 1. Staff Report, 2. Romtec Quote Package, 3. Restroom Proposal, 4. Trash Enclosure Proposal, 5. Trellis Shelters Proposal, 6. Romtec Sourcewell Contract
DATE: May 7, 2025

TO: Honorable Mayor and City Councilmembers

FROM: Development Services Department

TITLE: PURCHASE ORDER TO ROMTEC, INC. FOR FINAL DESIGN AND SUPPLY OF BUILDING MATERIAL FOR THE STRUCTURES AT THE PROPOSED EL CORAZON PARK SITE 1

RECOMMENDATION
title
Staff recommends that the City Council approve a purchase order to Romtec, Inc. ("Romtec"), in an amount not to exceed $554,973, for final design and supply of building material for the structures at the proposed El Corazon Park Site 1 and authorize the Financial Services Director, or designee, to execute the purchase order.
body
BACKGROUND AND ANALYSIS

On February 23, 2022, the City Council approved a Professional Services Agreement (PSA) for design of the proposed El Corazon Park Site 1 with Schmidt Design Group.

The following structures are included within the design of El Corazon Park Site 1:

* A modular multipurpose building consisting of restrooms, maintenance storage, electrical room, and telecommunication room as shown in Attachment 3 (approximately 1,000-square feet)
* A trash enclosure as shown in Attachment 4 (approximately 300-square feet)
* Four (4) trellis shelters as shown in Attachment 5.

Schmidt Design Group has been working with Romtec to provide specifications, design drawings, and renderings of the structures. Romtec designs, manufacturers, supplies, and constructs buildings and structures for all types of application. The Romtec team includes architects, engineers, manufacturers, and contractors.

Upon approval of the requested purchase order by the City Council, Romtec would provide the engineered plan set and complete submittals necessary for a building permit, as well as supply the building material necessary to construct the structures as specified in Attachment 2 and Attachment 6. Structure installation is not included as part of this purchase order; rather, it will be incorporated into the future construction contract for the proposed El Corazon Park Site 1.