DATE: December 2, 2026
TO: Honorable Mayor and City Councilmembers
FROM: Water Utilities Department
TITLE: PROFESSIONAL SERVICES AGREEMENT WITH N2W ENGINEERING, INC. FOR THE PRELIMINARY DESIGN OF THE LEISURE VILLAGE #1 LIFT STATION UPGRADES AND FINAL DESIGN AND SERVICES DURING CONSTRUCTION OF ELECTRICAL UPGRADES
RECOMMENDATION
title
Staff recommends that the City Council approve a Professional Services Agreement with N2W Engineering, Inc., in the amount of $274,775, to provide preliminary design of the Leisure Village #1 Lift Station and final design and services during construction of electrical upgrades; and authorize the City Manager, or designee, to execute the agreement upon receipt of all supporting documents.
body
BACKGROUND AND ANALYSIS
The Leisure Village #1 Lift Station, located at the intersection of Cannon Road and Leisure Village Drive, was constructed in 1984 to serve the residential area of Ocean Hills in the southeast region of the city. The station can convey approximately 0.38 million gallons of wastewater per day to the gravity system along Cannon Road that ultimately flows to the San Luis Rey Water Reclamation Facility.
The electrical gear for the lift station has reached the end of its useful life and replacement parts are no longer available due to the age of the equipment. The station has experienced several issues with controls and communications, which necessitate upgrades to ensure continued system reliability and performance. In addition, the existing electrical system does not comply with current standards and codes.
The City issued a Request for Proposals (RFP) on September 10, 2026, seeking qualified engineering consultants to provide preliminary design services, recommend a prioritized list of upgrades needed to extend the service life and reliability of the station, and to complete final design for the urgent electrical upgrades. The RFP also included engineering construction support services during the construction of...